Câu 14: 74-343: Managing Projects with Microsoft Project 2013

You are a project manager who uses Project Standard 2013, and your task list includes a flag field that indicates, with Yes or No, if a non-summary task represents a physical deliverable. Your project involves several tasks marked as deliverables, and management requires you to track how many deliverables are complete…

Nội dung câu hỏi

You are a project manager who uses Project Standard 2013, and your task list includes a flag field that indicates, with Yes or No, if a non-summary task represents a physical deliverable. Your project involves several tasks marked as deliverables, and management requires you to track how many deliverables are completed. The deliverable is considered completed when the Percent complete field is 100%.You need to create a formula to calculate the total number of deliverables that are completed. Which two steps should you perform? (Each correct answer presents part of the solution. Choose two.)

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Use the following formula: IIf([Physical Deliverable]=Yes And [% Complete]=100,1,0). — đáp án hiện tại
  2. B. Set Calculation for tasks and summary groups to Sum. — đáp án hiện tại
  3. C. Use the following formula: IIf([Physical Deliverable]=Yes And [% Complete]=100,0,1).
  4. D. Set Calculation for tasks and summary groups to Count All.

Cộng đồng

0 bình luận công khai. Tên thành viên được ẩn một phần.

Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.