Câu 13: 74-343: Managing Projects with Microsoft Project 2013

You are a project manager who uses Project Professional 2013. Two of your resources job share; Resource1 works Monday, Tuesday, and a half day Wednesday. Resource2 works the remaining work week. You need to set up their calendars to reflect the job-sharing arrangement. What should you do?

Nội dung câu hỏi

You are a project manager who uses Project Professional 2013. Two of your resources job share; Resource1 works Monday, Tuesday, and a half day Wednesday. Resource2 works the remaining work week. You need to set up their calendars to reflect the job-sharing arrangement. What should you do?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Open each resource and set a recurring exception to reflect the non-working days.
  2. B. Open each resource and amend the working time on each resource's calendar. — đáp án hiện tại
  3. C. Open each resource and set their Resource Availability units to 50%.
  4. D. Open each resource and use the Resource information dialog box to create a new calendar. Change the Default Work Week to reflect the working time.