Câu 13: 74-343: Managing Projects with Microsoft Project 2013
You are a project manager who uses Project Professional 2013. Two of your resources job share; Resource1 works Monday, Tuesday, and a half day Wednesday. Resource2 works the remaining work week. You need to set up their calendars to reflect the job-sharing arrangement. What should you do?
Nội dung câu hỏi
You are a project manager who uses Project Professional 2013. Two of your resources job share; Resource1 works Monday, Tuesday, and a half day Wednesday. Resource2 works the remaining work week. You need to set up their calendars to reflect the job-sharing arrangement. What should you do?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Open each resource and set a recurring exception to reflect the non-working days.
- B. Open each resource and amend the working time on each resource's calendar. — đáp án hiện tại
- C. Open each resource and set their Resource Availability units to 50%.
- D. Open each resource and use the Resource information dialog box to create a new calendar. Change the Default Work Week to reflect the working time.
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.
Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.