Câu 12: 74-343: Managing Projects with Microsoft Project 2013
You are a resource manager who uses Project Standard 2013. You manage all of your resources in a single plan, which acts as a Shared Resource Pool for other projects in your organization. Each resource needs to pass an annual exam in order to work on construction sites. You need to set up a method that allows you to p…
Nội dung câu hỏi
You are a resource manager who uses Project Standard 2013. You manage all of your resources in a single plan, which acts as a Shared Resource Pool for other projects in your organization. Each resource needs to pass an annual exam in order to work on construction sites. You need to set up a method that allows you to pick the renewal month for each resource. What should you do?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Rename the Resource Text1 Custom field to Exam Expiration Date. Enter the month when the exam expires. Select the correct expiration date for each resource.
- B. Use the Organizer to copy the Resource Finish1 Custom field from the Global.mpt. Select the correct expiration date for each resource.
- C. Rename the Resource Date1 Custom field to Exam Expiration Date. Create a Lookup table with values containing the last date of each month. Select the correct expiration date for each exam. — đáp án hiện tại
- D. Rename the Resource Month1 Custom field to Exam Expiration Date. Create a Lookup table with monthly values. Select the correct expiration month for each exam.
- E. Rename the Resource Flag1 Custom field to Exam Expired Date. Enter the expiration dates into a Lookup table. Select the correct expiration date for each