Câu 3: 74-343: Managing Projects with Microsoft Project 2013

You are a project manager who uses Project Professional 2013. You work on a construction project that requires propane as a fuel source for your equipment. The foreman requires that you enter project costs associated with all work completed on your project. The propane costs $5.00 per gallon, and the tank holds 500 ga…

Nội dung câu hỏi

You are a project manager who uses Project Professional 2013. You work on a construction project that requires propane as a fuel source for your equipment. The foreman requires that you enter project costs associated with all work completed on your project. The propane costs $5.00 per gallon, and the tank holds 500 gallons of propane. Each time the tank is refilled, you must pay a fee of $20. You need to enter the propane costs into your project schedule prior to filling the propane tank for the first time. What should you do?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Create a material resource with a material label of gallons. Enter $20 in the cost per use and $5.00 in the standard rate.
  2. B. Create a cost resource, add the resource to a task, and enter $25 in the actual cost. — đáp án hiện tại
  3. C. Create a material resource with a material label of gallons. Enter $20 in the standard rate and $5.00 in the cost per use.
  4. D. Create a cost resource, add the resource to a task, and enter $2520 in the actual cost.