Câu 2: 74-343: Managing Projects with Microsoft Project 2013

Your organization uses Microsoft Project 2013. You are finalizing the Project Schedule for a very complex project with over 100 resources. You need to ensure that all tasks are assigned to resources. What should you do?

Nội dung câu hỏi

Your organization uses Microsoft Project 2013. You are finalizing the Project Schedule for a very complex project with over 100 resources. You need to ensure that all tasks are assigned to resources. What should you do?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Use Task Usage view and look for Unassigned tasks.
  2. B. Use Resource Graph view and look for the Unassigned resource name.
  3. C. Use Resource Usage view and look for the Unassigned resource name. — đáp án hiện tại
  4. D. Use Resource Sheet view and look for Unassigned tasks.