CertyRush
Đang tải...
C CertyRush
Câu hỏi free preview

Câu 5: 74-343: Managing Projects with Microsoft Project 2013

You are a project manager, and your organization uses Project Professional 2013. You have created a detailed project schedule and have identified two tasks that are causing your resource to be overallocated. You need to use the Team Planner to reassign these tasks from the overallocated resources to underallocated res…

Nội dung câu hỏi

You are a project manager, and your organization uses Project Professional 2013. You have created a detailed project schedule and have identified two tasks that are causing your resource to be overallocated. You need to use the Team Planner to reassign these tasks from the overallocated resources to underallocated resources with the same skill set. What should you do?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Right-click the task and reassign it to the underallocated resource. — đáp án hiện tại
  2. B. Drag the underallocated resource on the task to reassign it.
  3. C. Drag one of the tasks from the overallocated resource to the Unassigned Tasks section.
  4. D. Right-click the resource and reassign it to the underallocated resource.

Cộng đồng

0 bình luận công khai. Tên thành viên được ẩn một phần.

Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.

Câu hỏi liền kề