Câu 6: 74-343: Managing Projects with Microsoft Project 2013
You are a senior project manager, and your organization uses Project Standard 2013. You are managing a large ERP project with both part-time and full-time resources. The part-time resources have strict contractual limitations regarding working days and hourly availability. You need to make sure the tasks for your part…
Nội dung câu hỏi
You are a senior project manager, and your organization uses Project Standard 2013. You are managing a large ERP project with both part-time and full-time resources. The part-time resources have strict contractual limitations regarding working days and hourly availability. You need to make sure the tasks for your part-time resources are only scheduled in the calendar during their agreed-upon working days and hours. What should you do?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Change the part-time resources' tasks to manually scheduled to ensure the dates do not go past the agreed-upon terms of their contract.
- B. Enter the availability start and end dates for each resource and change the percent of units to the agreed-upon amount in their contract.
- C. Enter the availability start and end dates for each resource and change the working time for each resource to only include days and hours agreed upon in their contract. — đáp án hiện tại
- D. Change the part-time resources' units to the percentage they are available and set task constraints to must finish on to ensure the dates do not go past the