Câu 6: 74-343: Managing Projects with Microsoft Project 2013

You are a senior project manager, and your organization uses Project Standard 2013. You are managing a large ERP project with both part-time and full-time resources. The part-time resources have strict contractual limitations regarding working days and hourly availability. You need to make sure the tasks for your part…

Nội dung câu hỏi

You are a senior project manager, and your organization uses Project Standard 2013. You are managing a large ERP project with both part-time and full-time resources. The part-time resources have strict contractual limitations regarding working days and hourly availability. You need to make sure the tasks for your part-time resources are only scheduled in the calendar during their agreed-upon working days and hours. What should you do?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Change the part-time resources' tasks to manually scheduled to ensure the dates do not go past the agreed-upon terms of their contract.
  2. B. Enter the availability start and end dates for each resource and change the percent of units to the agreed-upon amount in their contract.
  3. C. Enter the availability start and end dates for each resource and change the working time for each resource to only include days and hours agreed upon in their contract. — đáp án hiện tại
  4. D. Change the part-time resources' units to the percentage they are available and set task constraints to must finish on to ensure the dates do not go past the