Câu 7: 74-343: Managing Projects with Microsoft Project 2013
Your organization uses Project Professional 2013. A senior stakeholder in a project asks you to determine when a task is over budget by comparing the baseline cost of a task to the cost. Additionally, the senior stakeholder wants you to display a graphic indicator when the baseline cost is greater than the cost. You w…
Nội dung câu hỏi
Your organization uses Project Professional 2013. A senior stakeholder in a project asks you to determine when a task is over budget by comparing the baseline cost of a task to the cost. Additionally, the senior stakeholder wants you to display a graphic indicator when the baseline cost is greater than the cost. You write a formula to display the indicator, but it only displays for normal tasks and not for summary tasks. You need to make the indicator display for summary tasks. Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Within the Custom Field, set Calculation for task and group summary rows to Use Formula. — đáp án hiện tại
- B. Within the Custom Field, set Calculation for task and group summary rows to Maximum.
- C. Within the Graphical Indicators dialog box, check the Import Indicator Criteria button.
- D. Within the Graphical Indicators dialog box, check Summary rows inherit criteria from nonsummary row. — đáp án hiện tại