CertyRush
Đang tải...
C CertyRush
Câu hỏi free preview

Câu 10: MB-240: Microsoft Dynamics 365 for Field Service

You are a Dynamics 365 for Field Service administrator for a construction company. You need to schedule a work order for a group of resources that will work together for a set number of days, week, or months. How should you achieve the goal without scheduling the same requirements multiple times manually by using the…

Nội dung câu hỏi

You are a Dynamics 365 for Field Service administrator for a construction company. You need to schedule a work order for a group of resources that will work together for a set number of days, week, or months. How should you achieve the goal without scheduling the same requirements multiple times manually by using the schedule board (or with the schedule assistant)?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Use Facility Scheduling
  2. B. Use Multi-Resource Scheduling
  3. C. Use Resource Crew Scheduling — đáp án hiện tại
  4. D. Use Universal Resource Scheduling

Cộng đồng

0 bình luận công khai. Tên thành viên được ẩn một phần.

Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.

Câu hỏi liền kề