You are a Dynamics 365 for Field Service administrator for a construction company. You need to schedule a work order for a group of resources that will work together for a set number of days, week, or months. How should you achieve the goal without scheduling the same requirements multiple times manually by using the…
Nội dung câu hỏi
You are a Dynamics 365 for Field Service administrator for a construction company. You need to schedule a work order for a group of resources that will work together for a set number of days, week, or months. How should you achieve the goal without scheduling the same requirements multiple times manually by using the schedule board (or with the schedule assistant)?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Use Facility Scheduling
- B. Use Multi-Resource Scheduling
- C. Use Resource Crew Scheduling — đáp án hiện tại
- D. Use Universal Resource Scheduling