An audit team leader arrives at a steel fabrication organization that manufactures stairways to carry out a Stage 2 certification audit. At a meeting with the OHSMS Manager the auditor finds that the responsibility for worker consultation and participation lies with the managerial team. Select from the options four ac…
Nội dung câu hỏi
An audit team leader arrives at a steel fabrication organization that manufactures stairways to carry out a Stage 2 certification audit. At a meeting with the OHSMS Manager the auditor finds that the responsibility for worker consultation and participation lies with the managerial team. Select from the options four actions by the managerial team that encourage worker consultation and participation.
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Implementing a payment scheme to reward worker’s OHS performance
- B. Conducting toolbox talks on health and safety — đáp án hiện tại
- C. Threatening reprisals to whistleblowers
- D. Appointing worker’s representatives — đáp án hiện tại
- E. Implementing methods for engaging workers — đáp án hiện tại
- F. Ignoring worker’s suggestions
- G. Giving ownership of health and safety matters — đáp án hiện tại
- H. Promoting collaborating workers to higher positions