Câu 157: PgMP: Program Management Professional

A program manager is concerned that a program will be unable to achieve its intended benefits. How should the program manager handle this concern?

Nội dung câu hỏi

A program manager is concerned that a program will be unable to achieve its intended benefits. How should the program manager handle this concern?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Meet with the program management office (PMO) to review critical program success factors. — đáp án hiện tại
  2. B. Meet with the component project managers to reallocate resources within the program.
  3. C. Meet with the program stakeholders to determine if a reduction in program scope is acceptable.
  4. D. Meet with the component project managers to perform risk analysis.