Câu 158: PgMP: Program Management Professional
Program A is dependent upon program B to complete benefits sustainment for two benefits. Program A is on track to meet program benefits. However, programB's program manager has just advised that program B has been closed. What should program A's program manager update and review first with the stakeholders?
Nội dung câu hỏi
Program A is dependent upon program B to complete benefits sustainment for two benefits. Program A is on track to meet program benefits. However, programB's program manager has just advised that program B has been closed. What should program A's program manager update and review first with the stakeholders?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Benefits sustainment plan — đáp án hiện tại
- B. Benefits register
- C. Benefits management plan
- D. Benefits transition plan