Câu 58: PgMP: Program Management Professional

A program manager has been assigned to a program that has received approval of the program charter and for which a stakeholder register has been prepared. During stakeholder engagement planning, the program manager should consider which of the following stakeholders aspects?

Nội dung câu hỏi

A program manager has been assigned to a program that has received approval of the program charter and for which a stakeholder register has been prepared. During stakeholder engagement planning, the program manager should consider which of the following stakeholders aspects?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Attitude about the program, external political position, and technical expertise
  2. B. Level of influence and participation and attitude about the program
  3. C. Expectations of program benefits, level of influence, and organizational culture — đáp án hiện tại
  4. D. Level of support/opposition, technical expertise, and organizational culture