Câu 57: PgMP: Program Management Professional
A large program consists of several component projects and six project managers. The program governance board requests that all components within the program undergo user acceptance testing before being released to the production environment. Where should the program manager document this?
Nội dung câu hỏi
A large program consists of several component projects and six project managers. The program governance board requests that all components within the program undergo user acceptance testing before being released to the production environment. Where should the program manager document this?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Program governance plan
- B. Program requirements
- C. Component test plan and test cases
- D. Program quality management plan — đáp án hiện tại