Câu 202: PgMP: Program Management Professional

A biometrics firm has a facial recognition program with multiple components and project managers. The project manager from the mobile device division escalates a vendor-related risk to the program manager. After assessing the risk, the program manager determines that this risk may impact other projects within the prog…

Nội dung câu hỏi

A biometrics firm has a facial recognition program with multiple components and project managers. The project manager from the mobile device division escalates a vendor-related risk to the program manager. After assessing the risk, the program manager determines that this risk may impact other projects within the program. However, this risk has a low degree of impact and probability of occurring. What should the program manager do first?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Obtain a risk reserve from the executive sponsor, and execute a contingency plan.
  2. B. Communicate the risk to all project managers to manage at the component level.
  3. C. Add the risk details and analysis to the program risk register. — đáp án hiện tại
  4. D. Brainstorm with the project manager to develop an appropriate risk response.