Câu 202: PgMP: Program Management Professional
A biometrics firm has a facial recognition program with multiple components and project managers. The project manager from the mobile device division escalates a vendor-related risk to the program manager. After assessing the risk, the program manager determines that this risk may impact other projects within the prog…
Nội dung câu hỏi
A biometrics firm has a facial recognition program with multiple components and project managers. The project manager from the mobile device division escalates a vendor-related risk to the program manager. After assessing the risk, the program manager determines that this risk may impact other projects within the program. However, this risk has a low degree of impact and probability of occurring. What should the program manager do first?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Obtain a risk reserve from the executive sponsor, and execute a contingency plan.
- B. Communicate the risk to all project managers to manage at the component level.
- C. Add the risk details and analysis to the program risk register. — đáp án hiện tại
- D. Brainstorm with the project manager to develop an appropriate risk response.