Câu 201: PgMP: Program Management Professional
A global enterprise resource planning (ERP) program's scope includes designing and building a global template. Plans include a pilot implementation project to validate the template, to be followed by several rollout projects. During the build of the global template, a new government regulation mandates implementation…
Nội dung câu hỏi
A global enterprise resource planning (ERP) program's scope includes designing and building a global template. Plans include a pilot implementation project to validate the template, to be followed by several rollout projects. During the build of the global template, a new government regulation mandates implementation of a goods and services tax (GST). What should the program manager update?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Program communications management plan
- B. Benefits management plan — đáp án hiện tại
- C. Stakeholder engagement plan
- D. Benefits transition plan