Câu 85: PgMP: Program Management Professional
A program manager initiates a developmental program. Significant resources and funding are required for early activities until the program cost and budget estimates are complete. What should the program manager do to understand the financial environment?
Nội dung câu hỏi
A program manager initiates a developmental program. Significant resources and funding are required for early activities until the program cost and budget estimates are complete. What should the program manager do to understand the financial environment?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Map costs to the expected benefits realization.
- B. Establish intermediate budget based on historical information.
- C. Establish program financial framework. — đáp án hiện tại
- D. Obtain intermediate funding from the executive sponsor.