Câu 84: PgMP: Program Management Professional

A software company's program manager is conducting closing procedures for a program. At the last steering committee meeting, realized benefits were presented to the program governance board. What should the program manager do next?

Nội dung câu hỏi

A software company's program manager is conducting closing procedures for a program. At the last steering committee meeting, realized benefits were presented to the program governance board. What should the program manager do next?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Begin transitioning program resources, and update the resource and program management plans to reflect the change in the program's status.
  2. B. Initiate knowledge transfer with the receiving organization, and establish the program integration management plan.
  3. C. Update the financial, stakeholder, and contract management plans, and archive them in the program information repository.
  4. D. Obtain sponsoring organization approval to begin closeout procedures to transition benefits sustainment to the supporting organization. — đáp án hiện tại