A mature agile team welcomes a new member. Due to poor experiences with a previous team, the new member is reluctant to communicate. What should be the agile project leader do?
Nội dung câu hỏi
A mature agile team welcomes a new member. Due to poor experiences with a previous team, the new member is reluctant to communicate. What should be the agile project leader do?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Bring up the new member's impediments at the next meeting to demonstrate team support of input
- B. Assure the new member that inputs on impediments are valued, and demonstrate this at the next meeting — đáp án hiện tại
- C. Have a senior leader work with the new member to avoid a negative impact on team productivity
- D. Privately work with the new member to address any impediments