The risk profile of a project has increased beyond the upper threshold of tolerance. The product owner and project leader meet to discuss an approach for dealing with this. What should the team do next?
Nội dung câu hỏi
The risk profile of a project has increased beyond the upper threshold of tolerance. The product owner and project leader meet to discuss an approach for dealing with this. What should the team do next?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Add risk mitigation tasks to the backlog, then prioritize in current and upcoming sprints — đáp án hiện tại
- B. Add risk mitigation time to each requirement
- C. Apply the 80/20 rule, reserving 20 percent of each sprint's capacity for risk mitigation
- D. Hold all risks until they become issues, then add issue resolution tasks to the product backlog