Câu 3: PMI Agile Certified Practitioner

Stakeholders are displeased with the latest release of a product's software. While most stakeholders attended every sprint review, they were otherwise largely uninvolved in the project. What should the agile practitioner have done to ensure stakeholder satisfaction?

Nội dung câu hỏi

Stakeholders are displeased with the latest release of a product's software. While most stakeholders attended every sprint review, they were otherwise largely uninvolved in the project. What should the agile practitioner have done to ensure stakeholder satisfaction?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Communicated early and often, as outlined in the communications matrix
  2. B. Ensured engagement among stakeholders and the product owner — đáp án hiện tại
  3. C. Conducted additional stakeholder reviews and demos
  4. D. Worked with the product owner to prioritize user stories