Câu 4: PMI Agile Certified Practitioner
A product owner for two highly visible projects spends a great deal of time meeting with and reporting to senior stakeholders. The product owner is overwhelmed because both project teams request clarification on the requirements and the overall priorities. What should the agile project manager do?
Nội dung câu hỏi
A product owner for two highly visible projects spends a great deal of time meeting with and reporting to senior stakeholders. The product owner is overwhelmed because both project teams request clarification on the requirements and the overall priorities. What should the agile project manager do?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Provide both project teams with the highest priority needs
- B. Request the project team's questions in writing prior to the next meeting
- C. Facilitate a meeting with each team and the product owner to finds a solution — đáp án hiện tại
- D. Provide both teams with each project's documentation
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.
Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.