Câu 60: PMI Agile Certified Practitioner
An agile team's client has been asked to expedite the delivery of the next release. By delivering one month early, the company can generate US$40,000 more than expected for the quarter. What should the agile team do?
Nội dung câu hỏi
An agile team's client has been asked to expedite the delivery of the next release. By delivering one month early, the company can generate US$40,000 more than expected for the quarter. What should the agile team do?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Adhere to the new deadline and immediately advise the client that the schedule has been expedited
- B. Advise the client that it is best to continue as planned rather than introduce unforeseen risks by expecting the schedule — đáp án hiện tại
- C. Submit a change request to the client with a 50% increase in charges due to the new potential profit
- D. Request additional resources to meet the expedited deadline and obtain training for the new resources
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.
Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.