Câu 59: PMI Agile Certified Practitioner

The project team is ahead of schedule and beginning to gold-plate the feature included in the current sprint. What should the agile project manager do?

Nội dung câu hỏi

The project team is ahead of schedule and beginning to gold-plate the feature included in the current sprint. What should the agile project manager do?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Since the team has extra time, notify the product owner and secure approval for the extra work on this feature
  2. B. Encourage the team to document the improvement and prioritize it for the upcoming iteration, instead of building it now
  3. C. Instruct the Scrum Master to have the team use the extra time to complete the extra feature work in the current iteration
  4. D. Notify the product owner and have the product owner verify the backlog priority, then encourage team to continue working on the backlog — đáp án hiện tại