Câu 59: PMI Agile Certified Practitioner
The project team is ahead of schedule and beginning to gold-plate the feature included in the current sprint. What should the agile project manager do?
Nội dung câu hỏi
The project team is ahead of schedule and beginning to gold-plate the feature included in the current sprint. What should the agile project manager do?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Since the team has extra time, notify the product owner and secure approval for the extra work on this feature
- B. Encourage the team to document the improvement and prioritize it for the upcoming iteration, instead of building it now
- C. Instruct the Scrum Master to have the team use the extra time to complete the extra feature work in the current iteration
- D. Notify the product owner and have the product owner verify the backlog priority, then encourage team to continue working on the backlog — đáp án hiện tại
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.
Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.