Câu 28: PMI Construction Professional

A construction professional is considering contract structures for a small public facility. The program manager has advised that once the project budget has been determined there can be no cost increases or delivery delays. The scope is well-defined and the timeline is predictable. All prequalified contractors have co…

Nội dung câu hỏi

A construction professional is considering contract structures for a small public facility. The program manager has advised that once the project budget has been determined there can be no cost increases or delivery delays. The scope is well-defined and the timeline is predictable. All prequalified contractors have completed many similar projects using the standard design. Which contract structure should the construction professional use in this situation?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Prequalified competitive bid
  2. B. Unit price contract
  3. C. Job order contracting (JOC)
  4. D. Lump sum contract — đáp án hiện tại