Câu 27: PMI Construction Professional

To deliver a very complex mega build project, the organization decided to leverage a new technology and adopt a hybrid delivery approach throughout the project. During planning, the construction professional advised the project team to use an approach to predict the probability of different project outcomes related to…

Nội dung câu hỏi

To deliver a very complex mega build project, the organization decided to leverage a new technology and adopt a hybrid delivery approach throughout the project. During planning, the construction professional advised the project team to use an approach to predict the probability of different project outcomes related to cost and schedule. To which approach is the construction professional referring?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Monte Carlo simulation — đáp án hiện tại
  2. B. Delphi technique
  3. C. Parametric estimation
  4. D. Analogous estimation