Câu 26: PMI Construction Professional
A construction professional is having a dispute with one of the subcontractor project managers regarding the scope of work. The construction professional believes removal of an existing plant should be a part of the subcontractor's scope of work, but the subcontractor project manager disagrees, citing the signed contr…
Nội dung câu hỏi
A construction professional is having a dispute with one of the subcontractor project managers regarding the scope of work. The construction professional believes removal of an existing plant should be a part of the subcontractor's scope of work, but the subcontractor project manager disagrees, citing the signed contract. After reviewing the contract, the construction professional has a different interpretation of the written clause. What should the construction professional do next to rectify the situation?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Ask for a third-party mediator to intervene in the dispute between the two parties.
- B. Move to arbitration if the stalemate continues so site work can proceed without further delay.
- C. Call for a meeting with the subcontractor's team to clarify the difference of opinions. — đáp án hiện tại
- D. Have the project owner settle the dispute between the construction professional and the subcontractor.
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.