Câu 26: PMI Construction Professional

A construction professional is having a dispute with one of the subcontractor project managers regarding the scope of work. The construction professional believes removal of an existing plant should be a part of the subcontractor's scope of work, but the subcontractor project manager disagrees, citing the signed contr…

Nội dung câu hỏi

A construction professional is having a dispute with one of the subcontractor project managers regarding the scope of work. The construction professional believes removal of an existing plant should be a part of the subcontractor's scope of work, but the subcontractor project manager disagrees, citing the signed contract. After reviewing the contract, the construction professional has a different interpretation of the written clause. What should the construction professional do next to rectify the situation?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Ask for a third-party mediator to intervene in the dispute between the two parties.
  2. B. Move to arbitration if the stalemate continues so site work can proceed without further delay.
  3. C. Call for a meeting with the subcontractor's team to clarify the difference of opinions. — đáp án hiện tại
  4. D. Have the project owner settle the dispute between the construction professional and the subcontractor.

Cộng đồng

0 bình luận công khai. Tên thành viên được ẩn một phần.

Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.