Câu 10: PMI Construction Professional

A construction professional manages a construction project for their company. The project sponsor has a great deal of authority over project decisions. However, the construction professional discovers that the project sponsor is not interested in the project due to being insufficiently informed about the project statu…

Nội dung câu hỏi

A construction professional manages a construction project for their company. The project sponsor has a great deal of authority over project decisions. However, the construction professional discovers that the project sponsor is not interested in the project due to being insufficiently informed about the project status. What strategy should the construction professional utilize to ensure the project sponsor's continuous support?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Amend the project's risk register with the identified risk and take corrective action.
  2. B. Inform the project sponsor that they can contact the construction professional with any questions about the project.
  3. C. Update the project's communications management plan and manage key stakeholders closely. — đáp án hiện tại
  4. D. Ask upper management to make decisions on behalf of the project sponsor and keep the sponsor informed.