A general contractor uses prefab technology on their high-rise building project. During the design phase, the project team and the prefab specialist met on a weekly basis to resolve any technical issues, coordinate the design, and improve constructability. The project is currently in the construction stage, and the pr…
Nội dung câu hỏi
A general contractor uses prefab technology on their high-rise building project. During the design phase, the project team and the prefab specialist met on a weekly basis to resolve any technical issues, coordinate the design, and improve constructability. The project is currently in the construction stage, and the prefab components are being delivered to the site using the just-in-time (JIT) approach due to the on-site space constraints. The prefab coordinator alerts the construction professional that one of the installed components has a deficiency and needs to be replaced, which will cause delays in installation of the subsequent panels. What should the construction professional do next based on the impact resulting from this error?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Take steps to prepare for additional rework and redesign.
- B. Prepare for a contractual dispute between the parties.
- C. Calculate the possible cost overrun.
- D. Determine the possible schedule overrun. — đáp án hiện tại