Câu 37: PMI Construction Professional
A real estate development firm is working on defining the scope of work for a project to build a modern resort. The time line is tight and shareholders are pushing for the bid to be issued. The construction professional recommends involving all stakeholders in the scope definition exercise; however, the project sponso…
Nội dung câu hỏi
A real estate development firm is working on defining the scope of work for a project to build a modern resort. The time line is tight and shareholders are pushing for the bid to be issued. The construction professional recommends involving all stakeholders in the scope definition exercise; however, the project sponsor insists on involving only the project team to expedite the process. What should the construction professional do next?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Suggest involving all current key stakeholder while excluding future operational representatives.
- B. Agree with the sponsor as they have higher authority and the bid submission has a tight time line.
- C. Escalate the issue to upper management and request a meeting with all parties to resolve the situation.
- D. Highlight to the sponsor the importance of involving all key stakeholders in scope definition to reduce downstream change orders. — đáp án hiện tại