Câu 36: PMI Construction Professional
A construction project is in the planning phase of building a desalination plant. The construction professional's team has identified and logged a risk in the risk register, noting multiple root causes and has assigned responses to address each cause. How should the construction professional manage this risk moving fo…
Nội dung câu hỏi
A construction project is in the planning phase of building a desalination plant. The construction professional's team has identified and logged a risk in the risk register, noting multiple root causes and has assigned responses to address each cause. How should the construction professional manage this risk moving forward?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Monitor and evaluate the risk regularly and ensure the assigned responses are still appropriate. — đáp án hiện tại
- B. Classify the risk appropriately to ensure an effective response is assigned and the impact on the project is understood.
- C. Assess the risk quantitatively to include the probability and impact for each root cause.
- D. Identify the root cause with the most significant impact and track its associated response actions to completion.