Câu 3: PMI Construction Professional

While reviewing tender documents to determine their bid for a large construction project, the contractor's team submits some questions to gain a better understanding from the project owner regarding some missing items and a contradiction between the design drawing and the bill of quantities. Which document should the…

Nội dung câu hỏi

While reviewing tender documents to determine their bid for a large construction project, the contractor's team submits some questions to gain a better understanding from the project owner regarding some missing items and a contradiction between the design drawing and the bill of quantities. Which document should the construction professional ensure their team submits?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Request for proposal (RFP)
  2. B. Invitation to tender (ITT)
  3. C. Request for tender (RFT)
  4. D. Request for information (RFI) — đáp án hiện tại