A construction company is addressing the risk management for a new project. Senior leadership is requesting contingency estimates from the construction professional for this project. At this stage, the project team has held a brainstorming session and identified several risks. What should the construction professional…
Nội dung câu hỏi
A construction company is addressing the risk management for a new project. Senior leadership is requesting contingency estimates from the construction professional for this project. At this stage, the project team has held a brainstorming session and identified several risks. What should the construction professional do next?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Reduce or offset validated risks.
- B. Classify risks based on key categories.
- C. Arrange for risk mitigation to be implemented.
- D. Analyze the potential impact of each risk. — đáp án hiện tại