Câu 2: PMI Construction Professional

A construction company is addressing the risk management for a new project. Senior leadership is requesting contingency estimates from the construction professional for this project. At this stage, the project team has held a brainstorming session and identified several risks. What should the construction professional…

Nội dung câu hỏi

A construction company is addressing the risk management for a new project. Senior leadership is requesting contingency estimates from the construction professional for this project. At this stage, the project team has held a brainstorming session and identified several risks. What should the construction professional do next?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Reduce or offset validated risks.
  2. B. Classify risks based on key categories.
  3. C. Arrange for risk mitigation to be implemented.
  4. D. Analyze the potential impact of each risk. — đáp án hiện tại