Câu 14: PMI Construction Professional
A construction professional is assigned to a new build project and is currently preparing with the team to commence with the risk management activities. The team conducted interviews, reviewed project documents and lessons learned, and identified as many risks as possible. The team added the risks to the project's ris…
Nội dung câu hỏi
A construction professional is assigned to a new build project and is currently preparing with the team to commence with the risk management activities. The team conducted interviews, reviewed project documents and lessons learned, and identified as many risks as possible. The team added the risks to the project's risk register. What should the construction professional do once the risks have been identified?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Perform a quantitative risk analysis.
- B. Carry out a Monte Carlo simulation.
- C. Review the risks with the key stakeholders.
- D. Conduct a probability and impact assessment. — đáp án hiện tại