Câu 48: PMI Professional in Business Analysis
A business analyst assigned to review test output for a project realizes that an approved requirement has been missed. Which technique could the business analyst have used to ensure that requirements were delivered as stated?
Nội dung câu hỏi
A business analyst assigned to review test output for a project realizes that an approved requirement has been missed. Which technique could the business analyst have used to ensure that requirements were delivered as stated?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Use cased
- B. Requirements management plan
- C. Traceability matrix — đáp án hiện tại
- D. Work breakdown structure