CertyRush
Đang tải...
C CertyRush
Câu hỏi free preview

Câu 50: PMI Professional in Business Analysis

A major stakeholder of a project is surprised to learn that a particular requirement was not implemented during the latest launch. The business analyst tells the stakeholder that the requirement status was changed to “deferred”.What could have prevented the stakeholder from being surprised about the status change?

Nội dung câu hỏi

A major stakeholder of a project is surprised to learn that a particular requirement was not implemented during the latest launch. The business analyst tells the stakeholder that the requirement status was changed to “deferred”.What could have prevented the stakeholder from being surprised about the status change?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. The status should have been reviewed prior to project launch.
  2. B. The status should have been communicated to all project stakeholders. — đáp án hiện tại
  3. C. The status should have been updated in the traceability matrix.
  4. D. The status should have been communicated to the requirement’s source.

Cộng đồng

0 bình luận công khai. Tên thành viên được ẩn một phần.

Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.

Câu hỏi liền kề