Câu 25: PMI Project Management Office Certified Professional

An organization is forming a PMO. The team responsible for running the PMO is being recruited; it includes a mix of people from internal departments and external resources. One of the team members hired to work on the PMO has a lack of experience in certain services of the PMO that will be included in their assignment…

Nội dung câu hỏi

An organization is forming a PMO. The team responsible for running the PMO is being recruited; it includes a mix of people from internal departments and external resources. One of the team members hired to work on the PMO has a lack of experience in certain services of the PMO that will be included in their assignment. What should the PMO professional do?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Provide intensive training on the functional departments of the company and their particularities.
  2. B. Assign an experienced member from the PMO to mentor the less-experienced team member. — đáp án hiện tại
  3. C. Provide a self-training plan so that the new team member can study PMO theory at their own pace.
  4. D. Assign a team from the PMO to train the new member to enhance their performance.