Câu 106: PMI Risk Management Professional

At the completion of a small project, the risk manager performs a risk audit and finds that several identified risks had occurred, and the impact was significantly larger than expected. While the project remained on schedule, the project budget increased by 50%. The project met all risk response milestones and no addi…

Nội dung câu hỏi

At the completion of a small project, the risk manager performs a risk audit and finds that several identified risks had occurred, and the impact was significantly larger than expected. While the project remained on schedule, the project budget increased by 50%. The project met all risk response milestones and no additional, previously unidentified risks, occurred on the project. Based on this information, what risk management process improvement should the risk manager recommend for future similar projects?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Increase frequency of risk management meetings with the project manager.
  2. B. Revise the level of accuracy of probability and impact scores.
  3. C. Document the risk audit report and capture it in the lessons learned database. — đáp án hiện tại
  4. D. Expand the use of risk identification techniques.