Câu 105: PMI Risk Management Professional
While preparing for a project review meeting with leadership, the project team analyzes and checks its scope activities and discovers missing requirements. The project risk manager decides to hire a subcontractor to fulfill these newly discovered requirements. What risk strategy did the project risk manager use?
Nội dung câu hỏi
While preparing for a project review meeting with leadership, the project team analyzes and checks its scope activities and discovers missing requirements. The project risk manager decides to hire a subcontractor to fulfill these newly discovered requirements. What risk strategy did the project risk manager use?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Avoid
- B. Transfer — đáp án hiện tại
- C. Accept
- D. Mitigate