Câu 152: PMI Risk Management Professional
A project that was in the execution phase for the last six months was put on hold and was eventually cancelled after numerous scope related challenges. It was decided to re-plan the scope and divide the project into multiple projects to have better insight into end objectives. As part of the project start up, the proj…
Nội dung câu hỏi
A project that was in the execution phase for the last six months was put on hold and was eventually cancelled after numerous scope related challenges. It was decided to re-plan the scope and divide the project into multiple projects to have better insight into end objectives. As part of the project start up, the project manager is developing the risk planning for the project. What three artifacts should the project manager consult or review during this process? (Choose three.)
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Risk management plan
- B. Code of regulations
- C. Project contracts — đáp án hiện tại
- D. Risk register — đáp án hiện tại
- E. Lessons learned registers from analogous projects — đáp án hiện tại
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.