Câu 153: PMI Risk Management Professional
During a risk reassessment workshop with the project team and some external stakeholders, two key external stakeholders are overemphasizing the impact of a few project risks. This has led to a conflict. How should the risk manager handle this situation?
Nội dung câu hỏi
During a risk reassessment workshop with the project team and some external stakeholders, two key external stakeholders are overemphasizing the impact of a few project risks. This has led to a conflict. How should the risk manager handle this situation?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Request for a skilled facilitator to help resolve conflicts that have arisen.
- B. Use the assumption analysis techniques to validate the assumptions. — đáp án hiện tại
- C. Refer to the team’s ground rules on how to resolve conflicts.
- D. Run a sensitivity analysis to check which risks have the most impact.