Câu 33: PMI Risk Management Professional
After applying several risk identification techniques, the risk manager is ready to document project risks in the risk register, including risk name, risk statement, probability of occurring, and potential impact. After this information is complete, who is best suited to serve as risk owners?
Nội dung câu hỏi
After applying several risk identification techniques, the risk manager is ready to document project risks in the risk register, including risk name, risk statement, probability of occurring, and potential impact. After this information is complete, who is best suited to serve as risk owners?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Risk manager
- B. Project sponsors
- C. Project manager
- D. Project team members — đáp án hiện tại