Critical deliverables are delayed, because a key subject matter expert (SME) does not have enough time to allocate to the tasks. How could the situation be improved for the future?

Nội dung câu hỏi

Critical deliverables are delayed, because a key subject matter expert (SME) does not have enough time to allocate to the tasks. How could the situation be improved for the future?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Cross train others to reduce the SME workload. — đáp án hiện tại
  2. B. Introduce scope reductions to limit the reliance on SMEs.
  3. C. Replace the SME with resources, who are responsible for receiving output from the SME on their deliverables.
  4. D. Extend the project schedule timeline to accommodate availability of the SME.