Câu 150: PMI Risk Management Professional

Multiple new risks have come up on a project that were not included on the risk register. The project manager met with the team to explain that risk management is critical for the success of the project, and risk identification is key. What should the project manager do next?

Nội dung câu hỏi

Multiple new risks have come up on a project that were not included on the risk register. The project manager met with the team to explain that risk management is critical for the success of the project, and risk identification is key. What should the project manager do next?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Review assumptions and constraints around risks. — đáp án hiện tại
  2. B. Apply an iterative approach to risk identification.
  3. C. Determine the likelihood and impact of the risks.
  4. D. Develop the risk response plans for identified risks.