Câu 149: PMI Risk Management Professional

The project manager for project X was expecting the mobilization of critical equipment from another project, project Y. However, a day before the mobilization was scheduled, another project manager notifies project X’s project manager that the equipment would not be available for at least another month due to delayed…

Nội dung câu hỏi

The project manager for project X was expecting the mobilization of critical equipment from another project, project Y. However, a day before the mobilization was scheduled, another project manager notifies project X’s project manager that the equipment would not be available for at least another month due to delayed activities for project Y. This has jeopardized meeting a critical milestone for project X. How should project X’s project manager avoid this situation in the future?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Ask the other project manager to officially confirm the new date in writing
  2. B. Request that the other project manager inform if any additional delays are expected
  3. C. Request that the other project manager be added to relevant reports
  4. D. Prepare a contingency response plan to implement when delays occur — đáp án hiện tại