The risk manager and the project team conduct a risk brainstorming session for a new project. The risk manager wants to involve the entire project team in a group risk prioritization exercise for the identified risks. The project manager refuses the involvement of the entire project team due to resource concerns. What…

Nội dung câu hỏi

The risk manager and the project team conduct a risk brainstorming session for a new project. The risk manager wants to involve the entire project team in a group risk prioritization exercise for the identified risks. The project manager refuses the involvement of the entire project team due to resource concerns. What should the risk manager do?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Convince the project manager of the importance of the whole project team's involvement in the full risk process. — đáp án hiện tại
  2. B. Continue to involve the project team in the risk prioritization process and then discuss lessons learned with the project manager.
  3. C. Follow the project manager's instruction, as the project manager is the responsible party.
  4. D. Inform the sponsor about the project manager's decision and the disagreement between parties.