Câu 103: PMI Risk Management Professional
During a meeting to develop the risk management plan, the risk manager recognizes that risks may be identified that could also impact other projects that the company is pursuing. What should the risk manager do?
Nội dung câu hỏi
During a meeting to develop the risk management plan, the risk manager recognizes that risks may be identified that could also impact other projects that the company is pursuing. What should the risk manager do?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Take note of the extensive impact of these risks in the risk register
- B. Address the unique characteristics of these risks on a case-by-case basis
- C. Include an escalation process in the risk management plan
- D. Contact the risk managers of the other projects and inform them — đáp án hiện tại