Câu 94: PMI Risk Management Professional

A two-year project with a budget of US$2 million has completed about 60% of the work at the end of the first year. The actual cost incurred to complete the remaining 40% of work is about US$1.5 million. As a part of performing a specialized risk analysis, the calculated schedule performance index (SPI) is 1.2 and cost…

Nội dung câu hỏi

A two-year project with a budget of US$2 million has completed about 60% of the work at the end of the first year. The actual cost incurred to complete the remaining 40% of work is about US$1.5 million. As a part of performing a specialized risk analysis, the calculated schedule performance index (SPI) is 1.2 and cost performance index (CPI) is 0.53. How should the risk manager interpret such a low CPI value?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. The cost control processes are ineffective. — đáp án hiện tại
  2. B. The cost baseline is inaccurate.
  3. C. The actual reported costs are inaccurate.
  4. D. The cost related risks are effectively managed.