Câu 93: PMI Risk Management Professional
The risk manager for a project successfully establishes the risk management plan, the risk register and performs the qualitative risk analysis with the team. As the first step of the analysis, the risk manager develops the probability and impact scales. The scales are presented to the project manager, who refuses to a…
Nội dung câu hỏi
The risk manager for a project successfully establishes the risk management plan, the risk register and performs the qualitative risk analysis with the team. As the first step of the analysis, the risk manager develops the probability and impact scales. The scales are presented to the project manager, who refuses to accept the proposed scales. What did the risk manager overlook prior to developing probability and impact scales?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Gaining approvals for the developed risk register from the project manager
- B. Informing the project manager about the risk management process — đáp án hiện tại
- C. Evaluating and understanding the risk appetite of the stakeholders
- D. Interviewing the stakeholders and related parties