CertyRush
Đang tải...
C CertyRush
Câu hỏi free preview

Câu 168: PMI Risk Management Professional

A company has a project whose objective is to extract gold reserves from Field 1. However, another field closest to the company, Field 2, which has a higher probability of having twice as much gold reserves than Field 1. The risk manager requests the board of Directors to include Field 2 under the scope of the current…

Nội dung câu hỏi

A company has a project whose objective is to extract gold reserves from Field 1. However, another field closest to the company, Field 2, which has a higher probability of having twice as much gold reserves than Field 1. The risk manager requests the board of Directors to include Field 2 under the scope of the current project by management of change because the project's profitability will increase by 80%.What type of request is the risk manager describing?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. A request to increase project earnings — đáp án hiện tại
  2. B. A request to increase project resources
  3. C. A challenge to stakeholder thresholds
  4. D. A challenge to the project investment

Cộng đồng

0 bình luận công khai. Tên thành viên được ẩn một phần.

Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.

Câu hỏi liền kề