Câu 168: PMI Risk Management Professional
A company has a project whose objective is to extract gold reserves from Field 1. However, another field closest to the company, Field 2, which has a higher probability of having twice as much gold reserves than Field 1. The risk manager requests the board of Directors to include Field 2 under the scope of the current…
Nội dung câu hỏi
A company has a project whose objective is to extract gold reserves from Field 1. However, another field closest to the company, Field 2, which has a higher probability of having twice as much gold reserves than Field 1. The risk manager requests the board of Directors to include Field 2 under the scope of the current project by management of change because the project's profitability will increase by 80%.What type of request is the risk manager describing?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. A request to increase project earnings — đáp án hiện tại
- B. A request to increase project resources
- C. A challenge to stakeholder thresholds
- D. A challenge to the project investment